Will the transfer of responsibility from BGS Suppliers to the EDCs of Unaccounted for Energy (“UFE”), meter corrections, and inadvertent energy impact the process to establish Peak Load Contribution (“PLC”) or Network Service Peak Load (“NSPL”) values?


PLC and NSPL values are established by PJM, and not the EDCs.  The transfer of responsibility from BGS Suppliers to the EDCs of UFE, meter corrections, and inadvertent energy will not affect PJM’s process or calculations.